Media Kit » Try RailPrime™ Today! »
Progressive Railroading
Newsletter Sign Up
Stay updated on news, articles and information for the rail industry



This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.




railPrime
View Current Digital Issue »


RAIL EMPLOYMENT & NOTICES



Rail News Home Passenger Rail

11/16/2018



Rail News: Passenger Rail

Met Council taps Lunda, McCrossan to build Southwest light-rail line


The companies will construct 14.5 miles of double track and 16 light-rail stations and structures.
Photo – metrocouncil.org

advertisement

Minnesota's Metropolitan Council yesterday awarded a nearly $800 million contract to Lunda/C.S. McCrossan to build the Southwest light-rail project, an extension of Metro Transit's Green Line service.

The $2 billion project marks Minnesota's largest infrastructure project to date, council officials said in a press release.

Under the agreement, Lunda/McCrossan will build 14.5 miles of double track and 16 light-rail stations and structures. The companies also will construct 29 new bridges along the route, six pedestrian tunnels, two cut-and-cover light-rail tunnels and more than 100 retaining walls.

The Southwest project will share a 7.8-mile corridor with Twin Cities & Western Railroad and BNSF Railway Co.

Wisconsin-based Lunda Construction Co. specializes in bridge, railroad and industrial construction. Minnesota-based McCrossan is a highway/heavy civil general contractor with experience building light-rail lines.

McCrossan was one of the prime contractors that worked on the Minneapolis portion of the Green Line, which included rehabilitating the Washington Avenue Bridge over the Mississippi River to accommodate light-rail track. The company also worked on Metro Transit's Blue Line.

The council was able to award the civil construction contract after receiving a letter of no prejudice from the Federal Transit Administration (FTA) earlier this week. The letter makes early construction work on the project eligible for federal reimbursement upon award of a Full Funding Grant Agreement, which is expected in spring 2019, Met Council officials said.

The federal government would pay $929 million toward the project, with local funding covering the remaining costs.

Next month, the council expects to issue a limited notice to proceed, which will allow the contractor to start construction in designated areas. That will help keep the project on schedule while the council prepares its grant application to the FTA, Met Council officials said.

Activities this winter could include staffing and equipment mobilization, site clearance, demolition and utility work. Heavy construction is expected to start in 2019 and wrap up in 2022. Light-rail vehicle testing would follow in 2022 or 2023.

The Southwest line would operate from downtown Minneapolis through St. Louis Park, Hopkins, Minnetonka and Eden Prairie, Minnesota.