Amtrak completes First Street Tunnel upgrades


advertisement

Amtrak has completed its “Pause for Progress” infrastructure improvement project in the First Street Tunnel south of Washington, D.C., on time. Normal train operations resumed yesterday.

Over a planned nine-day service outage, crews replaced aging infrastructure at the A-Interlocking, a critical track and control point for Amtrak and Virginia Railway Express (VRE) trains traveling between Washington Union Station and Alexandria, Virginia. The work included replacing switches and crossovers, rehabilitating the tunnel track base and installing modern electric switch systems, Amtrak officials said in a press release.

During the project, crews replaced eight electric switch machines, two double-slip switches and one crossing diamond; rehabilitated 350 feet of track/tunnel base; installed 550 tons of ballast; replaced 1,000 feet of rail and 215 ties; and installed 2,500 feet of signal/electrical cable.

“This concentrated construction period allowed our teams to make significant improvements to critical infrastructure while limiting the amount of time it was out of service,” said Amtrak Executive Vice President, Strategy and Planning, Jennifer Mitchell. 