Newsletter Sign Up
Stay updated on news, articles and information for the rail industry
Stay updated on news, articles and information for the rail industry
RAIL EMPLOYMENT & NOTICES
Rail News Home
Maintenance Of Way
Rail News: Maintenance Of Way
Union Pacific Railroad recently began preliminary work on a $41.7 million track improvement project between Ft. Worth and Sweetwater, Texas.
The Class I plans to replace 46 miles of rail between West Fort Worth and Brazos; replace 243,500 ties between Brazos and Sweetwater; spread 114,740 tons of ballast between West Fort Worth and Sweetwater; surface and line 196 track miles; and replace surfaces at 184 grade crossings.
Crews will begin the bulk of the work May 8. Scheduled to be completed in mid-August, the project is part of UP's 2005 maintenance-of-way (MOW) capital plan, which calls for spending more than $1 billion to maintain and improve track within the road's 33,000-mile system.
UP already has begun MOW work in Arkansas, Oklahoma and Texas, including more than $27 million worth of projects designed to improve track at the railroad's south San Antonio yard and upgrade a Newport, Ark.-to-Harviell, Mo. mainline.
3/3/2005
Rail News: Maintenance Of Way
UP preps track in Texas for $42 million MOW project
advertisement
Union Pacific Railroad recently began preliminary work on a $41.7 million track improvement project between Ft. Worth and Sweetwater, Texas.
The Class I plans to replace 46 miles of rail between West Fort Worth and Brazos; replace 243,500 ties between Brazos and Sweetwater; spread 114,740 tons of ballast between West Fort Worth and Sweetwater; surface and line 196 track miles; and replace surfaces at 184 grade crossings.
Crews will begin the bulk of the work May 8. Scheduled to be completed in mid-August, the project is part of UP's 2005 maintenance-of-way (MOW) capital plan, which calls for spending more than $1 billion to maintain and improve track within the road's 33,000-mile system.
UP already has begun MOW work in Arkansas, Oklahoma and Texas, including more than $27 million worth of projects designed to improve track at the railroad's south San Antonio yard and upgrade a Newport, Ark.-to-Harviell, Mo. mainline.