Media Kit » Try RailPrime™ Today! »
Progressive Railroading
Newsletter Sign Up
Stay updated on news, articles and information for the rail industry



This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.




railPrime
View Current Digital Issue »


RAIL EMPLOYMENT & NOTICES



Rail News Home Passenger Rail

8/4/2016



Rail News: Passenger Rail

Cincinnati Streetcar gears up for pre-revenue service


advertisement

Photo: Cincinnati Streetcar website

The Cincinnati Streetcar will begin pre-revenue service on Aug. 7, marking the next step in preparing the streetcar for public use.

During the pre-revenue period, the streetcar operating and maintenance team can work out problems that arise and correct them before passenger service begins Sept. 9, Cincinnati Streetcar officials said in a press release.

In addition, all "behind-the-scenes" operations such as dispatching and supervision will be fully functioning.

The 3.6-mile Cincinnati Streetcar route has 18 stops throughout the city's downtown area. CAF USA built the vehicles for the line.

The Cincinnati Streetcar is owned and funded by the city, managed by the Southwest Ohio Regional Transit Authority and operated by Transdev.