Denver RTD to resume rail line testing, but contractor concerned about approval time


An RTD commuter train passes through a grade crossing.
Photo – Denver RTD

advertisement

Denver's Regional Transportation District (RTD) has received approval from the Colorado Public Utilities Commission (CPUC) to resume testing on the G Line commuter-rail route, local media reported yesterday.

RTD temporarily halted testing on the line last fall due to issues with grade crossing software. However, the Federal Railroad Administration (FRA) early last month gave its approval to continue limited testing on the line.

Despite the approvals, the project's contractor has raised concerns about how long it has taken to receive state and federal certification to operate the G Line.

Denver Transit Partners (DTP), the contractor for RTD commuter-rail lines, notified the agency that it is concerned about its "ongoing inability" to receive approval and final certification from the FRA and the CPUC.

The G Line is one of three commuter-rail projects in RTD's Eagle P3 project, which represents the United States' first set of newly built commuter-rail lines to use positive train control (PTC), RTD officials said in a press release.

In the notice, DTP claimed that there was a change in law governing certain FRA and CPUC approvals.

"The claim could impact the allocation of certain costs, the schedule for revenue service and payments to DTP for commuter-rail operations," RTD officials said.

Congress in 2015 passed the Positive Train Control Enforcement and Implementation Act, which extended the original deadline to implement the technology from 2015's end to 2018's end. The same year, Congress also passed the Fixing America's Surface Transportation Act, a long-term transportation funding bill.

However, neither law changed the "technical regulatory requirements for PTC systems," said FRA spokesman Marc Willis in an email.

"These acts of legislation dealt almost exclusively with extending the PTC system implementation deadline, providing railroads temporary relief from certain FRA regulations, and requiring railroads to submit to FRA a revised PTC implementation plan and implementation progress reports," Willis said. "The FRA has not 'reinterpreted design guidelines and regulations' and has not 'reversed technology mandates.'"

Willis added that the FRA is aware of DTP's notice and that the issue is a "local matter between RTD and DTP."

RTD is reviewing DTP's notice and will provide more information as it becomes available. The agency will continue to partner with DTP to complete testing and eventually open the G Line, RTD officials said in the news release.

RTD issued the release hours after the CPUC approved the resumption of G Line testing, The Denver Post reported yesterday.

Although RTD is waiting to receive the decision in writing, G Line testing could start in a week, according to the newspaper.

The line has been delayed for more than half a year as DTP works to fix a software issue at crossings along the B and A lines, The Post reported. All three commuter-rail lines will use the same crossing technology.