Media Kit » Try RailPrime™ Today! »
Progressive Railroading
Newsletter Sign Up
Stay updated on news, articles and information for the rail industry



This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.




railPrime
View Current Digital Issue »


RAIL EMPLOYMENT & NOTICES



Rail News Home Positive Train Control

5/4/2020



Rail News: Positive Train Control

GAO: Railroads report PTC progress, but some face 'compressed' schedules to meet deadline


Norfolk Southern Railway is one of the railroads required to implement PTC on its network.
Photo – gao.gov

advertisement

Most railroads required to implement positive train control (PTC) are "generally optimistic" about meeting the federally mandated deadline at the end of this year, according to a U.S. Government Accountability Office (GAO) report released last week.

Forty-two railroads — including Amtrak, 30 commuter and several freight railroads — were required to implement PTC by Dec. 31, 2018. Almost all received two-year extensions. By the end of 2019, more than three-quarters of the railroads were conducting advanced testing or had implemented PTC on their own tracks, but had work left to reach full implementation, GAO officials said in the report.

Full implementation means a railroad has implemented a PTC system certified by the Federal Railroad Administration (FRA) on all its own required territories and achieved interoperability with any railroads that operate on its tracks.

By Dec. 31, 2019, 17 of the 31 railroads that must achieve interoperability had done so.

Several face tight schedules for the rest of the work, making problems with software and vendors more acute, GAO officials said.

The GAO has previously identified longstanding software and vendor issues, which have grown more acute as many railroads face compressed schedules to meet the Dec. 31, 2020, deadline.

For example, five selected railroads have had to compress their schedules, meaning they must complete tasks in a shorter time than originally planned due to software issues or other unique circumstances. The compressed schedules and recurring challenges, as well as unexpected events such as the COVID-19 pandemic, create risks that could affect some railroads' ability to meet the extended deadline, the report states.

The FRA, vendors and railroads are taking steps to mitigate those risks, GAO officials said. For instance, the FRA has worked with railroads to identify solutions to technical problems and has targeted resources to regions identified as needing additional implementation assistance.

Moreover, FRA officials informed the GAO that they are "closely monitoring" the impact of the COVID-19 pandemic, such as the availability of supplies, staff and vendors.

Still, the FRA, vendors and railroads were generally optimistic that they'll overcome challenges to achieve full PTC implementation by year's end. Four railroads reported considering contingency plans if they, or their tenants, cannot meet the extended deadline, GAO officials said.

 

 

 



Contact Progressive Railroading editorial staff.

More News from 5/4/2020